The Pool Building Timeline: What to Expect During Each Stage
Marzo 19, 2025 3:40 - no comments yet | No one following this article yet.
Building a pool in your backyard is an exciting project, but it can also be complex and time-consuming. From choosing the right concrete pool builder to enjoying the final result, there are several stages in the pool building timeline that every homeowner should be prepared for. If you're considering a concrete pool, understanding each phase will help you manage expectations and ensure a smoother process. Below is a detailed breakdown of what to expect during each stage of the pool building process.
1. Initial Consultation and Design Phase
Duration: 1-3 weeks
The first stage in the pool-building timeline is the consultation and design process. During this phase, you’ll meet with your concrete pool builder to discuss your vision for the pool, the size, shape, and additional features (such as a hot tub, waterfall, or lighting). This is when you’ll begin to make crucial decisions, like the pool’s placement, design style, and any additional landscaping that will accompany it.
Key tasks include:
- Designing the Pool: Your pool builder will help you conceptualize the pool’s design and layout based on your preferences and the space available.
- Choosing Materials: Concrete pools offer flexibility in design, and your builder will provide options for finishes, tiles, coping materials, and more.
- Permits and Approvals: Your builder will secure necessary permits for the project. Depending on local regulations, this process could take some time.
During this phase, it's essential to communicate openly with your concrete pool builder to ensure the final design aligns with your expectations.
2. Excavation and Site Preparation
Duration: 1-2 weeks
Once the design is finalized and permits are in place, excavation is the next critical step. Excavation is one of the most labor-intensive parts of the pool-building process and can take anywhere from a few days to a couple of weeks, depending on the size and complexity of your pool.
Key tasks include:
- Excavating the Ground: Heavy machinery is used to dig the hole for your pool. The excavation team will ensure the hole is shaped to fit the pool's design, and any obstacles, like rocks or tree roots, are cleared.
- Site Preparation: After the pool’s shape is dug, the ground will be prepared for plumbing and electrical work.
This phase can get messy, but it is essential for ensuring the structural integrity of the pool.
3. Plumbing, Electrical, and Steel Framework
Duration: 1-2 weeks
With the excavation complete, the next step is to install the plumbing, electrical systems, and steel framework. For concrete pools, the steel framework is what holds the structure of the pool together. This is where the pool begins to take shape.
Key tasks include:
- Plumbing and Electrical: Your builder will install the necessary plumbing for filtration systems, pool heaters, jets, and other water features. Electrical wiring will also be run for lighting, heaters, and any other electrical components.
- Steel Reinforcement: Steel rebar is used to create a robust framework that reinforces the concrete shell of the pool. The steel framework is precisely placed according to the pool’s design specifications.
This stage involves a lot of behind-the-scenes work that is crucial for the functionality and safety of your pool.
4. Gunite or Shotcrete Application
Duration: 1 week
Once the steel framework is in place, it’s time to apply the concrete. For concrete pools, this step is typically done using gunite or shotcrete, two similar processes that involve spraying a dense mixture of concrete onto the steel reinforcement.
Key tasks include:
- Spraying Gunite or Shotcrete: A high-pressure hose is used to spray a thick concrete mixture onto the steel rebar, creating the pool’s shell.
- Shaping the Pool: While the gunite or shotcrete is applied, the pool builder will work to shape the pool’s contours, ensuring smooth curves and precise angles.
The concrete will need several days to cure and harden before the next steps can begin. This phase is a significant milestone, as the pool's structure is now in place.
5. Tile and Coping Installation
Duration: 1-2 weeks
After the concrete has cured, the next step is installing the finishing touches like tiles and coping. Coping refers to the material that forms the edge of the pool, while tiles are typically used for decorative purposes and to finish the waterline.
Key tasks include:
- Coping Installation: The builder will add coping around the perimeter of the pool. Popular options include stone, concrete, and natural materials like travertine or slate.
- Tile Installation: Decorative tiles are often added around the pool’s waterline or to accent features like steps, seating areas, or waterfalls.
This is a crucial phase to ensure your pool looks polished and complete.
6. Plastering and Pool Finishing
Duration: 1 week
With the pool’s structure and decorative elements in place, it’s time to apply the plaster or other finish to the pool's interior. Plaster is the most common finish for concrete pools, but you can also choose from other options like pebble finishes, tile, or aggregate finishes.
Key tasks include:
- Plaster Application: The interior surface of the pool is coated with plaster to create a smooth, watertight surface.
- Finish Selection: Depending on the finish you choose, the pool builder may use other materials like pebbles or quartz for added texture and visual appeal.
This phase is important for ensuring the pool is functional and aesthetically pleasing.
7. Decking, Landscaping, and Final Touches
Duration: 2-4 weeks
Now that the pool structure and finish are complete, it's time to focus on the surrounding area. Decking, landscaping, and any additional features you want to add will be installed during this stage.
Key tasks include:
- Decking: Concrete, pavers, or wood decking are popular options around the pool. This adds both style and functionality.
- Landscaping: Your concrete pool builder may work with landscapers to design the surrounding area, adding plants, trees, lighting, and other decorative elements.
- Final Touches: Any final elements, such as water features, fences, or custom lighting, will be installed.
This stage is essential to creating the perfect backyard oasis.
8. Filling the Pool and Testing Equipment
Duration: 1 week
After the construction is completed, your concrete pool will need to be filled with water. The pool equipment, including the filtration system, pumps, and heaters, will be tested to ensure everything works properly.
Key tasks include:
- Filling the Pool: Your pool builder will fill the pool with water, checking for leaks and ensuring everything is operating smoothly.
- Testing Equipment: The builder will run tests on the filtration, heating, and electrical systems to ensure the pool is functional and safe.
This is when you’ll see the pool come to life, and you’ll be able to admire the finished product.
9. Pool Cleaning and Final Inspection
Duration: 1 week
Before you can dive in, your pool will undergo a final cleaning and inspection. The builder will clean the pool’s interior to remove any debris, dirt, or construction materials. The final inspection ensures that everything is in working order.
Key tasks include:
- Cleaning: The pool’s interior will be scrubbed, and any leftover construction materials will be removed.
- Inspection: The builder will conduct a final inspection to ensure the pool meets all safety and quality standards.
Once this step is complete, your pool will be ready for you to enjoy!
10. Enjoy Your New Concrete Pool!
Duration: Ongoing
Now that the pool is complete, it's time to enjoy it! However, even after construction, ongoing maintenance and care are required to keep your pool in top shape. Regular cleaning, chemical testing, and equipment maintenance will ensure the longevity of your pool.
Conclusion
Building a concrete pool is a significant investment that can add value and enjoyment to your home. By understanding the pool building timeline, you can better prepare for each stage of the process and work closely with your concrete pool builder to ensure everything goes smoothly. From the initial consultation to the final touches, patience is key. In the end, you’ll have a beautiful, custom pool to enjoy for years to come.